Kingsley Kwaku David Amae
College of Technology Education, University of Education, Winneba
Abstract
As a result, a questionnaire was developed and administered to project managers of selected construction companies. The PCA extracted four factors namely, quality leadership, communication, motivation and experience supervisors. The analysis revealed that, among 28 critical factors, the 4 extracted factors had great effect on operatives’ labour productivity. This has implications for designing managerial strategies for improving labour productivity since the extracted factors are all managerial related factors. Based on the findings, the study has made recommendations for improving the productivity of site operatives in Ghana. Recommendations have also been made for further research.
Keywords: Labour Productivity, Site Operatives, Constructions Management